Posted By Rich Miller On February 25, 2008 @ 1:35 pm In Downtime | Comments Disabled
We will now keep a second switch, with its own built-in redundancy, in our data center to prevent a prolonged outage in the unlikely event of another switch failure. In addition, we are working with our phone vendor to create an automated failover system so calls will be routed directly to remote support sites in the case of a failure of our primary phone system.Globat, which is based in Los Angeles, was founded in 2001. Last year the company made three acquisitions, buying Hostaway, Newista and CompleteHostingSolutions.com.