Cisco Preps New Dallas Data Center

Cisco has been talking the talk with its Cisco’s Data Center 3.0 initiative, which includes new products to manage virtual assets. But it's also walking the walk, overhauling its in-house data centers to take advantage of the same capabilities.

As we've seen with many large virtualization and consolidation projects, that means building a new data center. In the next two weeks Cisco (CSCO) will open a new facility in Richardson, Texas (a suburb of Dallas), which will serve as the model for the company’s future facility builds. Cisco executives Sidney Morgan and Doug Gourlay discussed the new facility Tuesday at the Gartner Data Center Conference in Las Vegas.

"We were out of capacity," said Morgan, manager of IT engineering systems at Cisco. "We were physically out of floor space. After a while, the capacity issue was no longer even floor space, but power and cooling."

Cisco currently has 47 data centers with 195,000 square feet of raised floor space, which house 12,000 servers and more than 12,800 apps. Cisco has also acquired data centers through more than 120 acquisitions since 1997. That has given Cisco a larger footprint, but the company needed more advanced data centers. Morgan said many of Cisco’s data centers have the equivalent of Tier II infrastructure, and the company wanted more capacity and redundancy.

The project also gave Cisco the chance to evaluate new locations. "Since Cisco is a frugal company, we always bought affordable real estate," Morgan noted. "We ended up with data centers in a flood zone, and an earthquake zone in San Jose. So we did a lot of due diligence in where to put our new data center."

After weighing opportunities in Phoenix, Arizona and Boulder, Colorado, the company opted to retrofit an existing building it owned in the Dallas market. A lot of work went into the site location effort, and the availability of a suitable company-owned building with adjacent land was a key decision point.

The Richardson building is a four-story facility with a partial glass façade, which required some adaptation. "We’ve covered up the glass and reinforced the walls," said Morgan, who said the next data center – planned for an adjacent piece of land in Richardson – will likely be a one-story greenfield build.

The building’s mechanical systems were upgraded to the equivalent of Tier III on the Uptime Institute’s tier scale, while the electrical infrastructure was engineered for Tier IV-level redundancy.

"One of the challenges in Texas is that we had only 10 megawatt dual power feeds," said Morgan. "We’re hoping to get 50 megawatt dual feeds for the next data center. The way you have to design a data center these days is to see how much power you can get, and reverse engineer from there. It’s our experience that we’ve never been able to get enough megawatts to truly meet our needs."

The Richardson project is expected to pay for itself with an estimated $83 million in savings and cost avoidance. "This has been a two-year process," said Morgan. "There’s no easy button."

If you enjoyed this post subscribe to our RSS feed

AddThis Social Bookmark Button AddThis Feed Button

  By Rich Miller November 30, 2007 | Permalink | >Get Posts By E-mail

RELATED ENTRIES
Cisco, Dell Blogs Feud over FCoE vs. iSCSI - Apr 14, 2008
Nexus 5000: Next Step in Data Center 3.0 Push - Apr 08, 2008
Cisco Unveils New Switches for Data Center 3.0 - Jan 28, 2008


Comments